Grand River Dam Authority Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 8/30/19 At 3 PM on Friday, August 30: • Grand Lake elevation was 745.75 feet. Daily target elevation for August 30 is 743 feet. • At the direction of the United States Army Corps of Engineers, one (1) east spillway gate was open at Pensacola Dam, […]

Grand River Dam Authority News Release: Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 8/30/19 At 10:30AM on Friday, August 30: • Grand Lake elevation was 745.81 feet. Daily target elevation for August 30 is 743 feet. • At the direction of the United States Army Corps of Engineers, five (5) east spillway gates were open at Pensacola Dam, discharging […]

Grand River Dam Authority Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 08/29/19 At 11:30 AM on Thursday, August 29: • Grand Lake elevation was 746.40 feet. Daily target elevation for August 29 is 743 feet. • At the direction of the United States Army Corps of Engineers, five (5) east spillway gates were open at Pensacola Dam, […]

Grand River Dam Authority Floodwater Release Bulletin

At 4:30 PM on Tuesday, August 27: • Grand Lake elevation was 747.39 feet. Daily target elevation for August 27 is 743 feet. • At the direction of the United States Army Corps of Engineers, five (5) east spillway gates were open at Pensacola Dam, discharging 11,942 cubic feet per second (cfs) of water. • […]

Grand River Dam Authority News Release: Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 08/16/19 At Noon on Friday, August 16: • Grand Lake elevation was 745.42 feet. Daily target elevation for August 12 is 743 feet. • At the direction of the United States Army Corps of Engineers, one (1) main spillway gate was open at Pensacola Dam, discharging […]

Grand River Dam Authority Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 08/15/19 At 3 PM on Thursday, August 15: • Grand Lake elevation was 745.48 feet. Daily target elevation for August 15 is 743 feet. • At the direction of the United States Army Corps of Engineers, one (1) east spillway gate was open at Pensacola Dam, […]

Grand River Dam Authority Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 08/13/19 At 1 PM on Tuesday, August 13: • Grand Lake elevation was 746.21 feet. Daily target elevation for August 13 is 743.14 feet. • At the direction of the United States Army Corps of Engineers, seven (7) east spillway gates were open at Pensacola Dam, […]

Grand River Dam Authority Floodwater Release Bulletin 08/12/19

At 2 PM on Monday, August 12: • Grand Lake elevation was 745.93 feet. Daily target elevation for August 12 is 743.21 feet. • At the direction of the United States Army Corps of Engineers, one (1) main spillway gate was open at Pensacola Dam, discharging 688 cubic feet per second (cfs) of water. • […]

Grand River Dam Authority Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 07/25/19 At 12 PM on Thursday, July 25: • Grand Lake elevation was 746.68 feet. Daily target elevation for July 25 is 744 feet. • At the direction of the United States Army Corps of Engineers, one (1) main spillway gate was open at Pensacola Dam, […]

Grand River Dam Authority Floodwater Release Bulletin

Grand River Dam Authority News Release For immediate release: 07/24/19 At 1 PM on Wednesday, July 24: • Grand Lake elevation was 746.75 feet. Daily target elevation for July 24 is 744 feet. • At the direction of the United States Army Corps of Engineers, one (1) main spillway gate was open at Pensacola Dam, […]